NGCP Update

NGCP Update

Update on the unscheduled power interruption in parts of Quezon, Camarines Sur, and Camarines Norte on 18 October 2023 at 11:52AM

As of 5:00AM, NGCP dispatched 2 line gang to patrol Gumaca-Lopez-Tagkawayan 69kV Line again and maintenance group to repair circuit breaker at Gumaca Substation.

NGCP is exerting all efforts to restore the line at the soonest possible time.

We apologize for the inconvenience brought by the unscheduled power interruption.

Source: National Grid Corporation of the Philippines (NGCP)

Source: Quezon PIO